7-7-7 delayed by about a year
(3 posts)-
Posted 8 hours ago #
-
Cllr Booth asked about this at TEC June meeting. One issue has been, given the length of the route, waiting for a bunch of existing TRO/TTRO/ETRO orders to run their course, before they can ETRO the full 44 route. The last order they’re waiting for concludes in August; then advertise order from fhen, appoint contractor, work to implement in Feb 2026.
No idea if this explains the fact the original go-ahead was 2022 or if there was also a bit of fuddle duddling along the way.
Posted 7 hours ago # -
Think it was EdinBUG I picked up the 2022 timeline from - you can watch Cllr Booth’s question and the response about delays at 35m into the webcast at https://edinburgh.public-i.tv/core/portal/webcast_interactive/996034
Posted 7 hours ago #